Frequently Asked Questions
Implementation
Q: Is the Project providing any Weekend support for Go-Live? Are the Regional Go-Live office hours for live assistance at the User level or the County Level?
A: Yes, the CWDS Help Desk will provide 24/7 coverage for organizations post Go‑Live. If Santa Clara requires in‑person weekend support, that request should be included in their Go‑Live Support Plan so the Project can assess staffing availability and determine whether on‑site weekend coverage can be accommodated.
Regional Go‑Live Office Hours are designed for direct user-level assistance but organized at the regional grouping level. Counties may send any number of users, super users, or local support staff to attend; sessions are facilitated by Project teams and provide real‑time help with navigation, issue identification, and questions during Go‑Live.
Q: Can the Project provide documentation identifying the new required fields in CWS-CARES that Sacramento County can use to guide staff on which case information should be reviewed and updated at Go-Live, rather than waiting until staff next interact with a case?
A: All mandatory database fields are marked TRUE in the CWS-CARES Data Dictionary, under the “MANDATORY” column in the “Columns” tab. All Application required fields are marked with an asterisk (*) on the screen. The Data Dictionary is available on the CWS-CARES Data Dictionary Teams Channel. To request access to this channel, please contact the CWDS Data Management Mailbox.
Q: What happens if there are outstanding issues close to or beyond the 6 month read-only timeframe for CWS/CMS? Will the read-only period of CWS/CMS be extended so that Organizations can validate all the information?
A: Per the California Welfare and Institutions Code (WIC), "The existing CWS/CMS operations and functionality shall be maintained at a level that is at least commensurate with its December 2015 status and shall not be decommissioned prior to the full statewide implementation of the CWS-CARES in all counties. For purposes of this subdivision, “full statewide implementation” means after all existing CWS/CMS core system functionality has been replaced in CWS-CARES and has been implemented in all 58 counties for a minimum of six months with no significant defects outstanding."
Q: Will all data issues be fixed within the 6-month read-only timeframe for CWS/CMS post CWS-CARES Version 1 Go-Live? What’s the plan if not?
A: When CWS/CMS is in read-only mode, there will be no changes being made to CWS/CMS. CWS-CARES will become the system of record, and remaining data issues would be addressed in CWS-CARES.
Q: We’ve been given a schedule for the publication of updated and new ACLs/ACINs, but will there be any official communication from the project about updated or new guidance from the state on the implementation of CWS-CARES? When would that be? What can Implementation Leads (ILs) share with organizations when asked?
A: The Project is working on developing guidance concerning topics on the implementation of CWS-CARES and how it affects users. The guidance would include information surrounding system changes and will likely be published in early 2027. Please note that policy-related guidance will be issued by specific programs and policy areas affected within CDSS.
Q: Will counties receive the 76 updated and approved ACLs and ACINs?
A: Although the Go-Live date has been adjusted to December 7, 2026, to allow additional time for stabilization and readiness, the Project Team is still proceeding with the planned communication schedule for All County Letters (ACLs) and All County Information Notices (ACINs). Many letters are planned to be released closer to the CWS-CARES V1 Go-Live date. However, some letters may extend further to allow time for screenshots and other content that reflects how the system will actually appear at CWS-CARES V1 Go-Live.
Q: Will the release date of CWS-CARES Version 1 (CARES V1) be adjusted?
A: At an ad hoc CWS-CARES Board of Directors meeting on September 3, 2026, the following decisions were voted and approved:
Go-Live Date: The system launch is moved to Monday, December 7, 2026. This later date gives counties more time to complete data validation and continue with readiness activities before the system goes live.
Post–Go-Live Release Strategy: After the December launch, the system will receive two scheduled releases, one in March 2027 and another in May 2027. This approach gives additional time after Go-Live to stabilize the system and thoroughly validate functionality before enhancements are introduced. All planned enhanced stories are expected to be completed by May 1, 2027.
Cutover Plan: For the transition from current systems to CWS-CARES, CWS/CMS will switch into read-only on Thursday, December 3, 2026 at 5 PM.
For full details, see the Important Update: CWS-CARES Go-Live Date Adjusted to December 7, 2026 communication on the CWDS website.
Q: What is the final disposition of the Essential Stories?
A: There were 313 total stories considered and discussed to determine essentiality for Go-Live launch.
- 83 enhancement stories delivered in Version 1.1 by March 1, 2027;
- 115 enhancement stories delivered in Version 1.2 by May 1, 2027.
Q: What is the plan for system cutover, and how will downtime be minimized?
A: The plan for system cutover, as voted and approved by the Board of Directors on September 3, 2026, is to switch CWS/CMS to read‑only on Thursday at 5 p.m. This approach minimizes the amount of time counties operate in read‑only mode and helps reduce overall downtime. Because the cutover occurs shortly before Go‑Live, final validation and remediation are limited to one day prior, which reduces the time available for pre‑launch validation and issue resolution.
For full details, see the Important Update: CWS-CARES Go-Live Date Adjusted to December 7, 2026 communication on the CWDS website.
Q: What factors will counties be told must be met during the go/no‑go decision process?
A: ELT received a walkthrough on August 24, 2026. The 60-day checklist can be obtained from CWDA.