To support the transition to CWS-CARES, the CWDS Project Team decided to conclude CARES-Live releases. The CARES-Live Release 2.8.36 has been tentatively scheduled for February and this will be the final release unless a critical event occurs that requires an additional update.
The CARES-Live team will review and assess the stories in the backlog to finalize the scope for the remaining releases. The below list will provide the information of the remaining releases and their Go-live dates:
- CARES-Live Release 2.8.34 – July 31, 2025
- Scope: Security enhancements and infrastructure updates, including as Elasticsearch upgrade.
- CARES-Live Release 2.8.35 – November 20, 2025
- Scope: Security enhancements and infrastructure updates.
- CARES-Live Release 2.8.36 – February 2026
- Scope: Security enhancements and infrastructure updates.